Genoa Nodes Delivered

Genoa Nodes Delivered

Published: 19 Dec 2024 by NEMO Team

The AMD Genoa partition for NEMO2 was delivered on December 4th. This partition consists of 106 compute nodes with 192 cores and 768 GB RAM each (total >20k cores). In addition, four APU nodes with 4x AMD Instinct MI300A accelerator cards each and nine machines with 4x NVIDIA L40S each for machine learning and AI will be available in NEMO2.

As the acceptance of the storage has been delayed, we have not yet been able to launch NEMO2 this year. However, we have made the Milan nodes in NEMO1 available so that calculations are still possible in December and January. We will try to get the storage up and running in January and create instructions for the data transfer to the new system.

Happy holidays!

NEMO2 Genoa

Latest Posts

NEMO2 Production Mode

NEMO2 has officially launched, transitioning from a testing phase to full production with expanded hardware, including AMD Instinct MI300A and Nvidia L40A nodes. NEMO1 is being phased out, with limited resources available until May 31st. Users are encouraged to transition to NEMO2 and consult the wiki for details.

NEMO2 Conda

NEMO2 uses Miniforge for conda environments, offering a streamlined setup with conda-forge as the default repository. The Miniforge module auto-initializes conda, simplifying environment activation without modifying shell profiles.

Genoa Nodes Delivered

The AMD Genoa, Machine Learning and AI partitions for NEMO2 were delivered on December 4th. The acceptance of the storage has been delayed, so that NEMO2 could not yet start this year. However, calculations with the Milan nodes in NEMO1 are still possible.